Project Summary
Project Summary
Sector Name : POWER.
Agency Name : THDC INDIA LIMITED.
Project Name : DHUKWAN SMALL HYDRO PROJECT.

Reported Date : 06-MAR-20

Monthly Report : 1 / 2020

  

   

Total/Pending/Completed Milestone - 8 / 0 / 8

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
195.420294.6

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
279.0643.170322.23

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20140/012/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
34.670

Ministry Review Date

LatestLastPhysical Progress (%)Status
30-JUL-190Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks