Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : KBUNL-MUZAFFARPUR TPP STAGE-II- SUBSIDIARY (2X195 MW).

Reported Date : 07-NOV-17

Monthly Report : 9 / 2017

  

   

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3984.0303984.03

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3290.44003290.44

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20130/09/2017

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks