Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : GREEN ENERGY CORRIDORS INTER-STATE TRANSMISSION SCHEME -PART B.

Reported Date : 15-MAY-19

Monthly Report : 3 / 2019

  

   

Total/Pending/Completed Milestone - 9 / 4 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3705.613705.613705.61

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2441.9155.802597.7

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20183/20193/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5600

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks