Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : GREEN ENERGY CORRIDORS INTER-STATE TRANSMISSION SCHEME (ISTS) - PART A.

Reported Date : 21-AUG-18

Monthly Report : 6 / 2018

  

   

Total/Pending/Completed Milestone - 8 / 0 / 8

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1479.301479.3

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
864.8632.260897.12

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20173/20186/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2350

Ministry Review Date

LatestLastPhysical Progress (%)Status
09-MAY-18100Completed

Monthly Status

Background Information

Project completed & commissioned in June 2018.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks