Project Summary
Project Summary
Sector Name : POWER.
Agency Name : DAMODAR VALLEY CORPORATION.
Project Name : BOKARO THERMAL POWER STATION-A.

Reported Date : 01-OCT-18

MOU Status : Project Under MOU for 2016-2017

Monthly Report : 7 / 2018

Cost Overrun (%)-   88.79

Time Overrun (Months)-    N.A.

Total/Pending/Completed Milestone - 14 / 0 / 14

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
231304366.64

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
348404813965

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20110/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone