Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYSTEM STRENTHENING ASSOCIATED WITH MUNDRA UMPP (PART-A).

Reported Date : 10-JAN-18

Monthly Report : 11 / 2017

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
244.190244.19

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
71.951.430123.33

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20180/011/2017

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
500

Ministry Review Date

LatestLastPhysical Progress (%)Status
10-AUG-17100Completed

Monthly Status

Background Information

Project completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks