Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : CONNECTIVITY FOR KUDANKULAM 3 AND 4 (2000MW) WITH INTERSTATE TRANSMISSION SYSTEM.

Reported Date : 28-MAY-18

Monthly Report : 3 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
162.110162.11

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
73.951.10125

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20180/03/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
400

Ministry Review Date

LatestLastPhysical Progress (%)Status
22-DEC-17100Completed

Monthly Status

Background Information

Project completed & commissioned in March 2018.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks