Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : REMOVAL OF CONSTRAINTS IN 400KV BAYS EXTENSIONS AT 400KV VEMAGIRI SS.

Reported Date : 05-JUL-18

MOU Status : Not Under MOU for 2016-2017

Monthly Report : 4 / 2018

Cost Overrun (%)-   0

Time Overrun (Months)-    -4

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
207.880207.88

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
111.50-94.517

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20180/03/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
450

Ministry Review Date

LatestLastPhysical Progress (%)Status
09-MAY-18100Completed

Monthly Status

Background Information

Project completed & commissioned in March 2018.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone