Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : TELANGANA SUPER THERMAL POWER PROJECT PHASE I.

Reported Date : 10-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 1 / 2025

Cost Overrun (%)-   3.76

Time Overrun (Months)-    39

Total/Pending/Completed Milestone - 39 / 0 / 39

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
10598.98010998

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
10437.710010437.71

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20200/02/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone