Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : NORTH EASTERN REGION STRENGTHENING SCHEME IV.

Reported Date : 28-MAY-18

Monthly Report : 3 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
409.190409.19

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
27.4185.10212.5

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20180/05/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1250

Ministry Review Date

LatestLastPhysical Progress (%)Status
22-DEC-1752Completed

Monthly Status

Background Information

Work under progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks