Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYSTEM FOR ULTRA MEGA SOLAR POWER AT TUMKUR (PAVAGADA) KARNATAKA PHASE-I.

Reported Date : 15-NOV-18

Monthly Report : 9 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
810.480810.48

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
484.344.20528.5

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20180/09/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
183.10

Ministry Review Date

LatestLastPhysical Progress (%)Status
11-SEP-18100Completed

Monthly Status

Background Information

Project completed & commissioned in September 2018. 400KV D/C Tumkur Pool - Hiriyur line completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks