Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : ASSOCIATED TRANSMISSION SYSTEM FOR NABINAGAR-II TIPS.

Reported Date : 17-JUL-19

Monthly Report : 5 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
790.13790.3790.3

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
573.841.40575.24

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20196/20195/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
18.240

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

WORK UNDER PROGRESS.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks