Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : PAKRI BARWADIH COAL MINING PROJECT.

Reported Date : 09-JUN-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2022

Cost Overrun (%)-   24.81

Time Overrun (Months)-    N.A.

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4237.9605289.25

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3381.3428.603409.94

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20174/20190/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed