Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRAMISSION SYSTEM FOR SOLAR PARK AT BHADLA RAJISTHAN.

Reported Date : 04-DEC-19

Monthly Report : 10 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1429.3801429.38

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
993.6656.801050.46

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20197/201910/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
46.5546.55

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks