Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : AUGMENTATION OF TRANSFORMATION CAPACITY IN SOUTHERN REGION.

Reported Date : 21-AUG-18

Monthly Report : 6 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
167.750167.75

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
74.8111.81086.62

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20190/04/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
500

Ministry Review Date

LatestLastPhysical Progress (%)Status
09-MAY-18100Completed

Monthly Status

Background Information

Project completed & commissioned in June 2018. Extn. at 400/220KV Pondicherry S/stn. completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks