Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL HYDRO-ELECTRIC POWER CORPORATION.
Project Name : 50 MW SOLAR POWER PROJECT.

Reported Date : 09-MAY-18

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2018

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
287.480273.68

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0110.1577.42187.57

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20180/03/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
0250

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

First phase 25 MW capacity commissioned on 01.02.2018. 50MW Solar Power Project in Tamil Nadu fully commissioned on 23.03.2018 Commissioning certificate for 50MW Solar Power Project, Tamil Nadu issued by TANGEDCO on 23.03.2018.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone