Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYSTEM ASSOCIATED WITH IPPS OF NAGAPATTINAM/ CUDDALORE AREA PACKAGE A.

Reported Date : 07-FEB-19

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 12 / 2018

Cost Overrun (%)-   42.83

Time Overrun (Months)-    36

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
95501364

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1136111.6601247.66

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20150/012/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
185.50

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Line completed on 31.12.18

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Court cases0/00/0OverNormal
Court cases0/00/0OverNormal

Ongoing Milestone

Completed Milestone