Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYSTEM ASSOCIATED WITH GADARWARA STPS OF NTPC PART-B.

Reported Date : 15-NOV-18

Monthly Report : 9 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
222502225

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1477178.0201655.02

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20180/09/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
403.50

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Line commissioned in June 2018.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks