Project Summary
Project Summary
Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : TRANSMISSION SYSTEM STRENGTHENING ASSOCIATED WITH VINDHYACHAL V.

Reported Date : 07-FEB-19

Monthly Report : 12 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
175001750

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
967368.0401335.04

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20180/012/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
567.90

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Line commissioned on 31.12.18

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks