Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : TALAIPALLI COAL MINING PROJECT.

Reported Date : 09-JUN-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2022

Cost Overrun (%)-   0

Time Overrun (Months)-    N.A.

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
300417780

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1142.277.9601150.23

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/201911/20190/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone