Sector Name : POWER.
Agency Name : POWER GRID CORPORATION OF INDIA LIMITED.
Project Name : 400KV D/C TEESTA III - KISHANGANJ TRANSMISSIAN LINE (JV).

Reported Date : 08-MAR-19

Monthly Report : 1 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
77116241624

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1445.51131.6901577.2

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20137/20182/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
258.510

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks