Project Summary
Project Summary
Sector Name : POWER.
Agency Name : THDC INDIA LIMITED.
Project Name : KHURJA SUPER THERMAL POWER PROJECT.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 21 / 3 / 18

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
11089.4213276.1613276.16

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
12364.61130.1385.7912580.53

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20230/08/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
747.120

Ministry Review Date

LatestLastPhysical Progress (%)Status
21-MAY-2596Ongoing

Monthly Status

Background Information

• SG Pkg- All facilities of Unit-1 are operational. Unit-2 BLU was done on 11.04.25 and steam blowing completed on 30.05.25. Post-steam blowing restoration works nearing completion. Coal feeding system, FGD and AHP works in progress. In ESP, ATT of Pass-F, E, D, C and B completed, erection in Pass-A in progress. Fly-Ash Silo system is ready for Unit-1 and in advance stage of progress for Unit-2. • TG Pkg- Unit-1 is in operation since COD on 26.01.25. Unit-2 TG on Barring Gear achieved on 25.03.25. MDBFP is ready, TDBFP-1 and 2 put on barring gear. ST-2 and UAT-2A and 2B successfully charged. All 03 GTs of Unit-2 along with UT-2A and 2B are ready for charging. SPBD and IPBD erection also done. LP and HP By-pass, TG DCS and turbine governing system are ready. • Switchyard Pkg- is operational and power is being evacuated. • Railway Siding Pkg- Railway Siding is operational for coal transportation. • Cooling Tower Pkg- CT-1 is operational, CT-2 is also ready for operation. • Coal Handling Plant pkg- Coal, Limestone and Gypsum handling systems are operational along with WT-1 and 2 and SR-1 and 2, Coal Crusher and Lime-crusher House. 377 no. of coal rakes received and stacked at Khurja stockyard so far. WT-3 complex system erection work in advance stage. • CW System Equipment Package- RWPH and CWPH facilities are operational. • Water Treatment Plant & Misc. pkg- UF-RO Plant, DM make-up, DM regeneration pumps, clarifiers are operational. Coal Handling Effluent Treatment plant (CHETP) is also ready. Fire-Fighting system in TPs and conveyers is operational for Unit-1. • Ash Dyke Package- Lagoon-1 and 2 are in service, OFL and Lagoon-3 is ready for charging. • Make-up Water System is operational.• SG Pkg- Main Boiler-1 Light-Up done on 21.03.24. FOPH,Air-compressor,Chimney-1 ready. Boiler-1&2,ESP-1&2,FGD-1&2, Ash-Handling System, Pipe&Cable-Rack, Transformers, Cable-tray&Coal Conveyer structure,Chimney-2 work in progress. Raw Water Reservoir-1 operational, Reservoir-2 nearing completion. • TG Pkg-TG-1 Barring Gear done on 09.12.23. DC System commissioned. ST-1 charged. all CEP of Unit-1 commissioned. ACW,DMCW,Boiler Feed Water System ready. Unit-1 GT-1,2 ready for commissioning,GT-3 readiness for commissioning and Unit-2 Turbine, Condenser erection in progress. • Switchyard Pkg- 400 kV Switchyard successfully charged. Transmission line and Sub-station is ready for power evacuation. • Railway siding Pkg- Construction of majority bridges done, ROR,Trough-Wall,CRB,S&T,OHE works,Rail linking in progress. Engine rolling on Railtrack conducted from downline to plant yard. • CT Pkg- CT-1 ready with fill media, Switchgear building, outlet channel reay. Fan erection, cabling in progress. CT-2 fill-media installation in progress,Switchgear building &Outlet channel nearing completion. • Coal Handling Plant pkg- In CFP-1,Structure/equipment erection of WT-1 complex, TPs, Conveyors, CCH, Cable Galleries/Trestles,SR-1,LSCH, LCC, Pent house nearing completion. WT-2 ready for erection. Civil work in WT-3, SR-2 &Coal Path-2 in progress. • CW System Equipment Package-Equipment supply almost completed, erection&commissioning in progress. • CW System Civil Works Package- RWPH and CWPH operational. • Water Treatment Plant & Misc. pkg- DM water available. HRSCC PT-CW, UF-RO DM plant operational. MCC room-CWT, dosing shed, Booster-Pump house,CHEPT plant in progress. • Ash Dyke Package- Filling of COT, Sand blanketing,Dyke formation in Lagoon-1,2,3&OFL completed, Impervious lining, slope dressing levelling, Toe-Drain, Water Escape Structure,Geo-textile work in progress. • Make-up Water System- facility is functional to supply water to Plant.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks