Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : PATRATU STPP-I (3X800MW).

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    36

Total/Pending/Completed Milestone - 34 / 19 / 15

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
17112017112

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1628718.18016305.18

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20230/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
26500

Ministry Review Date

LatestLastPhysical Progress (%)Status
13-DEC-2481Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone