Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : ROURKELA PP-II EXPANSION (1X250 MW) - NSPCL.

Reported Date : 09-JUN-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2022

Cost Overrun (%)-   28.69

Time Overrun (Months)-    39

Total/Pending/Completed Milestone - 10 / 0 / 10

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1885.132311.82426

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2050.8.0902050.89

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20183/20223/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
245.23429.14

Ministry Review Date

LatestLastPhysical Progress (%)Status
95Completed

Monthly Status

Background Information

Project is already under commercial operation

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone