Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : DEVIKOT SOLAR 90MW.

Reported Date : 06-FEB-23

Monthly Report : 1 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
501.290524.83

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
466.8954.590521.48

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20211/202312/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
73.080

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks