Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : SAMBHU KI BHURJ SOLAR 250 MW.

Reported Date : 10-AUG-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 7 / 2022

Cost Overrun (%)-   0

Time Overrun (Months)-    11

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1522.7101522.71

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1224.5331.8159.411315.75

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/202111/20228/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
315.250

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information

Full capacity of 250 MW has been commissioned.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone