Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : KAYAMKULAM SOLAR 70 MW.

Reported Date : 14-JUL-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 6 / 2022

Cost Overrun (%)-   0

Time Overrun (Months)-    13

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
403.620403.62

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
201.8843.650245.53

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20211/20227/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
68.610

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information

Project fully commissioned and declared commercial w.e.f. 24.06.2022.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone