Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : FATEHGARH SOLAR 296MW.

Reported Date : 10-AUG-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 7 / 2022

Cost Overrun (%)-   0

Time Overrun (Months)-    11

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1749.3101749.31

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1365.2462.0414.331441.61

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20211/20238/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
265.170

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information

Project Commissioned and COD declared.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone