Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : ETTAYAPURAM SOLAR 230MW.

Reported Date : 06-FEB-23

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 1 / 2023

Cost Overrun (%)-   0

Time Overrun (Months)-    15

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1316.2201316.22

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1016.5493.984.621115.14

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/202112/202212/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information

Project Commissioned and COD declared w.e.f. 15.12.2022.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone