Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : ANTA SOLAR 90 MW.

Reported Date : 10-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 1 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
382.220382.22

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
497.1700497.17

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/03/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

CMCS building finishing work in progress. Power Transformers received. MMS Piling work (98%) and Boundary Wall work in progress. Modules package awarded by NTPC and supply started at site (100/135 MWp)

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone