Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : BHENSARA 320 MW.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   25.51

Time Overrun (Months)-    32

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1221.731533.381533.38

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1128.145.855.431139.42

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20223/20253/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Ongoing

Monthly Status

Background Information

Entire Capacity Commissioned on 20.03.2025.692 acres registered in the name of NTPC REL. Balance Land acquisition out of total tentative 1340 acres in progress by the agency. Module supply started at site, 400MWp received at site. Balance BOIs ordering in progress.