Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : GUJARAT 200 MW (GUVNL TENDER).

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   24.62

Time Overrun (Months)-    44

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
842.271049.611049.61

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
767.911.75.01769.67

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20223/20263/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
65.1Ongoing

Monthly Status

Background Information

63/200 MW Commissioned till Jan-25 , 477/592 Acres acquired, Work stopped due to law-and-order issues, Storage area set on fire & major material damaged.BOIs procurement in progress by agency. Land due diligence and transfer in progress. Land registration of 108/188 acres & 128/200 acres done in the name of NTPC REL at Kankachiyala & Rupakheda location respectively. Modules PO placed and supply started at site.(250/300MWp)

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone