Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
38
|
Total/Pending/Completed Milestone -
5
/
5
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
a) 239 acre (97%) out of 245 Acre land registered and verification of balance land is in progress.
b) 66.16 out 102 MWp Solar PV modules received at site. Balance quantity is in transit.
c) Erection of PV modules and Module Mounting Structure is in progress. 28.32 MWp out of 102 MWp PV modules installed.
d) Connectivity granted by GETCO on Bagodara Substation.
e) LD of 5.6 Crores imposed has been imposed by GUVNL.
f) 35 MWp modules are stuck at Customs due to non-payment by Contractor. | - Work awarded to M/s Svaryu Energy Limited on 06.05.2021. Contract agreement signed on 20.09.2021.
- 238.44 Acre (87%) out of 245 Acre land registered and verification of balance land is in progress.
- 66.2 MWp out of 102 MWp Solar PV modules received at site.
- Erection of PV modules and Module Mounting Structure is in progress. 28.32 MWp out of 102 MWp PV modules installed.
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |