Project Summary
Project Summary
Sector Name : POWER.
Agency Name : SATLUJ JAL VIDYUT NIGAM LIMITED.
Project Name : Bagodara Solar Power Project.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    38

Total/Pending/Completed Milestone - 5 / 5 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
339.350339.35

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
317.310.28317.59

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20220/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
15.380

Ministry Review Date

LatestLastPhysical Progress (%)Status
03-JUN-2551.22Ongoing

Monthly Status

Background Information

a) 239 acre (97%) out of 245 Acre land registered and verification of balance land is in progress. b) 66.16 out 102 MWp Solar PV modules received at site. Balance quantity is in transit. c) Erection of PV modules and Module Mounting Structure is in progress. 28.32 MWp out of 102 MWp PV modules installed. d) Connectivity granted by GETCO on Bagodara Substation. e) LD of 5.6 Crores imposed has been imposed by GUVNL. f) 35 MWp modules are stuck at Customs due to non-payment by Contractor.- Work awarded to M/s Svaryu Energy Limited on 06.05.2021. Contract agreement signed on 20.09.2021. - 238.44 Acre (87%) out of 245 Acre land registered and verification of balance land is in progress. - 66.2 MWp out of 102 MWp Solar PV modules received at site. - Erection of PV modules and Module Mounting Structure is in progress. 28.32 MWp out of 102 MWp PV modules installed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone