Project Summary
Project Summary
Sector Name : POWER.
Agency Name : SATLUJ JAL VIDYUT NIGAM LIMITED.
Project Name : PARASAN SOLAR POWER PROJECT.

Reported Date : 30-DEC-22

Monthly Report : 12 / 2022

  

   

Total/Pending/Completed Milestone - 5 / 0 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
392.30465

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
314.74124.70439.44

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20220/011/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
50105

Ministry Review Date

LatestLastPhysical Progress (%)Status
14-NOV-22100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks