Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : DAYAPAR WIND ENERGY PROJECT 150MW.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    25

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
937.80937.8

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
787.2811.611.22800.11

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20236/20256/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Ongoing

Monthly Status

Background Information

140/150 MW Commissioned on till Mar-25. Balance 10 MW Ready for Commissioning.50MW capacity commissioned w.e.f. 04.11.2023. WTG Supply and Erection work in progress. 70 nos. WTG erected. 73 out of 75 land parcels registered in the name of NTPC REL.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone