Reported Date :
07-JAN-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
12
/
2024
|
Cost Overrun (%)- 11.38
|
Time Overrun (Months)-
24
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
• The project is being executed by Bundelkhand Saur Urja Ltd (A Joint Venture between NHPC Ltd. and UPNEDA). Letter of Award for EPC Contract including O&M for 10 years issued on 17.03.2021. PPA has been signed between BSUL and UPPCL on 28.04.2022.
• Project partially commissioned during July-Aug-2022 with capacity of 26 MW. UPNEDA on 21.03.2024 issued CoD certificate for commissioning of balance 39 MW capacity on 07.03.2024.
• The supply of required 94 MWp solar pv modules for project has been completed. Other balance & minor activities are under progress. DC capacity addition has been completed for the available modules Other balance & minor activities are also in progress.
| • Letter of Award for EPC Contract including O&M for 10 years issued on 17.03.202. Project partially commissioned during July-Aug-2022 with capacity of 26 MW. UPNEDA on 21.03.2024 issued CoD certificate for commissioning of balance 39 MW capacity on 07.03.2024.
• UPPCL provided extension of time of SCOD of Project upto 31.03.2024 without levy of Liquidated damages.
• The supply of module was mainly affected due to global supply chain disruption because of COVID-19 and subsequent impact of BCD w.e.f. 01.04.2022.
• The supply of 38 MWp SPV out of balance 56 MWp modules has been completed. 02 MWp module in transit and Inspection of balance module is scheduled on April’24.
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |