Power House Access Tunnels & Adits (i.e., Adit from MAT to Pressure shaft bottom & Adit to TRT) is completed. Power House Excavation (PH Central Gullet, TC Central Gullet & Drainage Gallery) has achieved 350 cum, Pressure Shaft excavation achieved total Quantity of 1200 cum, Surge chamber excavation achieved total quantity of 100 cum.
The Concrete Lining of TRT through Gantry is in progress and a total 63 m Concrete Lining has been achieved during the month
| • Power House Excavation (Power House Cavern Central Gullet, Transformer Cavern Central Gullet & drainage gallery): 24700 cum excavation done during the month [Cumulative progress - 167000 Cum (58%) out of 290000 Cum].
• Pressure shaft erection chamber Excavation: 2900 cum excavation done during the month [Cumulative progress - 40200 cum (63%) out of 64000Cum].
• Dam abutment excavation: 20100 cum excavation done during the month [Cumulative progress – 281800 cum (81%) out of 350000 Cum].
• Underground excavation is in progress at TRT, Surge Chamber and multiple Adits.
• River Chenab was successfully diverted through DT-2 on 27.01.2024.
|