Civil Works: Concreting of Dam & Intake stands completed. In stilling basin, 2008 cum of concreting was placed during May’25 with cumulative 36629 cum concreting out of 37,500 cum. In May’25, HRT overt lining of 345 m done with cumulative 3768 m out of 6488 m. In Power House including TRC, cumulative 29129 cum concreting has been achieved out of 36,435 cum.
HM Works: Erection of all 04 Radial gates completed in all respect. Out of 195 ferrules, cumulative 194 No. of ferrules of the Pressure shaft & Penstock liners have been completed.
E&M Works: Unit-1 Boxing-up completed. Unit- 2: Boxing-up works are in progress. Unit-3: Stator and Rotor lowered in pit on 23.01.2025 and 26.03.2025 respectively. Turbine assembly works are in progress.
| Civil Works: Total 1469 cum concrete placed in Dam, Stilling basin, Intake and Power house area during Mar’2024. In HRT, 143 m heading excavation done during Mar’2024. Cumulative Heading excavation of 2294.80 m achieved out of 2694 m and 1151.50 m cumulative overt lining completed out of 6488 m.
HM Works: Erection of radial gate-4 completed. Welding work of Skin plates and stiffener of spillway radial gate-3 in progress. Positioning of wall plates of spillway radial gate-2 is completed. Erection of bottom and middle skin plates of spillway radial gate-1 is in progress. Erection of Intake Service Gate-1, 2 & 3 and their Rope Drum Hoist of 30 Ton capacity is completed. Erection of emergency gate is in progress. Cumulative 132 nos. of ferrules have been completed out of 194 no.
E&M Works: Unit-1: Stator and Rotor has been lowered in the generator pit. Turbine and MIV assembly works are in progress. Unit-2: Stator, Rotor and Turbine assembly is in progress. Unit-3: Erection of pit liner, pressure balancing pipe, and other pipes are completed. Concreting completed upto generator barrel after erection of spiral casing. Runner shifted to PH premises.
|