Project Summary
Project Summary
Sector Name : POWER.
Agency Name : SATLUJ JAL VIDYUT NIGAM LIMITED.
Project Name : GURHAH SOLAR POWER PROJECT.

Reported Date : 02-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 1 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    4

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
466.820466.82

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
237.21209.060446.27

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20230/012/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1500

Ministry Review Date

LatestLastPhysical Progress (%)Status
20-NOV-23100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone