Project Summary
Project Summary
Sector Name : POWER.
Agency Name : SATLUJ JAL VIDYUT NIGAM LIMITED.
Project Name : RAGHANESDA SOLAR POWER PROJECT.

Reported Date : 05-APR-24

Monthly Report : 3 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
642.150642.15

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
174.47340.050514.52

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20230/02/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3500

Ministry Review Date

LatestLastPhysical Progress (%)Status
09-JAN-24100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks