Reported Date :
16-OCT-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
10
/
2024
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
4
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Project commissioned on 08.08.2024 and COD declared on 07.10.2024. | Work awarded to M/s Larsen & Toubro Limited L&T Construction on 29.11.2022. Contract agreement signed on 29.12.2022.
- Standard penetration test and anchor pulling test completed. Anchor installation is in progress.
- Complete supply of floaters (2,21,982 nos.) received at site.
- Final route survey for 33 kV Transmission Line completed. Tower erection work and stringing work completed.
- Complete supply of Solar PV modules (120 MWp) received at site and 115.84 MWp solar modules assembly launched.
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |