Project Summary
Project Summary
Sector Name : POWER.
Agency Name : SATLUJ JAL VIDYUT NIGAM LIMITED.
Project Name : OMKARESHWAR FLOATING SOLAR POWER PROJECT (90 MW).

Reported Date : 16-OCT-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 10 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    4

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
646.170646.17

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
576.8223.950600.77

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20240/08/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
500

Ministry Review Date

LatestLastPhysical Progress (%)Status
17-SEP-24100Completed

Monthly Status

Background Information

Project commissioned on 08.08.2024 and COD declared on 07.10.2024.Work awarded to M/s Larsen & Toubro Limited L&T Construction on 29.11.2022. Contract agreement signed on 29.12.2022. - Standard penetration test and anchor pulling test completed. Anchor installation is in progress. - Complete supply of floaters (2,21,982 nos.) received at site. - Final route survey for 33 kV Transmission Line completed. Tower erection work and stringing work completed. - Complete supply of Solar PV modules (120 MWp) received at site and 115.84 MWp solar modules assembly launched.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone