Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : KHAWDA 1255MW SOLAR PROJECT (KHAWDA SOLAR PARK).

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    17

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
7179.5407179.54

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4462.12252.08303.675017.87

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20242/20262/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
85Ongoing

Monthly Status

Background Information

Land Allotment Completed, Modules Installation work is under progress, Transmission line work is under progress.Geotech and Topography completed. Equipment Engg. and BOI ordering in progress. MMS Supply 70% completed. MMS Piling 20% completed and column erection in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone