Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : BHADLA-II 500MW SOLAR PV PROJECT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    18

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2598.9202598.92

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1705.7052.361758.06

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20249/20259/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
55Ongoing

Monthly Status

Background Information

Land Acquisition Completed , Modules Installation work is under progress , Transmission line work Completed.Land and Connectivity and BOS Package awarded, site mobilization in progress. Land approval obtained, from Rajasthan Cabinet. Land lease to be signed. Module Supply started.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone