Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : SHAJAPUR 325MW SOLAR PV PROJECT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   3.13

Time Overrun (Months)-    15

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1530.4901578.34

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1197.3310.312.411210.05

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20246/20256/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
90Ongoing

Monthly Status

Background Information

205/325 MW Commissioned till Mar-25, Land Acquisition Completed, Modules Installation work is under progress, 33 kV Transmission Line Completed.Geotech completed. MMS Piling, IDT Foundation, CMCS civil work and fencing work in progress. Ordering of major BOIs including modules completed and supplies started. Module supply started at site.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks