Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : TALCHER THERMAL POWER PROJECT STAGE III(2X660 MW).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   5.87

Time Overrun (Months)-    7

Total/Pending/Completed Milestone - 22 / 20 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
11844012539

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1356.091282230.652868.74

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20270/012/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
13-DEC-2421.4Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone