Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : KERANDARI COAL MINING PROJECT.

Reported Date : 01-AUG-25

Monthly Report : 7 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
15532896.642896.64

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2002.3592.82-.172095

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20193/20253/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
332332

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks