Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : KERANDARI COAL MINING PROJECT.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   86.52

Time Overrun (Months)-    64

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
15532896.642896.64

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
01976.1126.242002.35

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20193/20253/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
332332

Ministry Review Date

LatestLastPhysical Progress (%)Status
64Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone