Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : SINGRAULI SUPER THERMAL POWER PROJECT, STAGE-III (2X800 MW).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 22 / 22 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
17195.31017195.31

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1300.62.2266.991569.79

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20300/02/2030

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
13-DEC-24.5Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks