Reported Date :
15-APR-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
• Long Term Access applied on 16.03.2023 at Khavda-I ISTS Sub-station. Due to unavailability of spare capacity, connectivity was offered by CTU at KPS-III instead of KPS-I during the meeting held on 29.03.2023. KPS-III has the scheduled commissioning date of Jan-2026. Project activities being aligned with the commissioning of ISTS substation at KPS-3, Khavada.
• 100% land (3100 Acre) acquired. Land sub-lease agreement signed on 29.01.2025.
• The Connectivity Agreement (Stage-1) was signed with M/s CTUIL on 25.02.2025. The connectivity to the project shall be provided by CTUIL at KPS-3 by 16.11.2026.
• Design & Engineering activities under process and Pull-Out Test on test pile under progress.
• Contractor is being regularly followed up to take up necessary steps to align the project commissioning with the readiness of Transmission Infrastructure at KPS-3 ISTS sub-station and within the time period of 02.03.2026 as extended by IREDA. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |