Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : NOKH SOLAR PV PROJECT 735 MW.

Reported Date : 03-JUN-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   4.51

Time Overrun (Months)-    15

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4189.174378.174378.17

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
00151.79151.79

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20247/20257/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
95Ongoing

Monthly Status

Background Information

245/735 MW Commissioned in Mar-25. Balance 490/735 MW Ready for Commissioning.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone